Water Main Replacement – County of San Bernardino – 2009
We Replaced a 12’’ Steel Water Main running under the Sheep Creek Aqueduct crossing. This project have a very tight schedule because the water in the Aqueduct had to be lowered to perform this work. They gave us 5 day of lower water, we finished in 3 and a half.